QPM Energy’s Isaac Power Station is designed to supply additional electricity to the Queensland grid when demand is high. The112 MW gas-fired plant is the first stage of the Isaac Energy Hub and will sitalongside QPM Energy’s existing gas processing and compression facility near Moranbah.
Orion Group was engaged to provide civil engineering and detailed design services for the extension of the Isaac Power Station at Moranbah, Queensland.
The project required a coordinated, buildable civil solution that responded to the highly specialised operational, structural and spatial requirements of the proposed gas turbines and switching yards, while also addressing the site's earthworks, access, drainage and servicing needs.
Orion's scope included detailed civil design and documentation for Operational Works approval, incorporating earthworks, internal roadworks, stormwater management, water and sewer infrastructure, driveway connections, RPEQ-certified drawings and supporting approval documentation.
A key design challenge was coordinating constrained site levels, equipment pads and associated earthworks around the substantial machinery required for the power station.
Establishing an efficient and adaptable earthworks strategy was therefore critical to achieving a functional layout without introducing unnecessary retaining structures or construction complexity.
Rather than developing the civil levels around fixed assumptions, Orion worked closely with the broader project team to understand the operational requirements of each component and identify where flexibility remained within the equipment arrangement.
The detailed civil design also coordinated tie-ins to existing infrastructure and integrated earthworks, roadworks, stormwater management, water, sewer and gas-related interfaces with the complex infrastructure they support.
The coordinated approach delivered a practical and fully functional civil solution for a constrained site dominated by large-scale mechanical and electrical infrastructure.
The client benefited from a civil design that optimised earthworks and reduced the need for retaining structures, helping minimise construction costs. Simplified civil works improved constructability, while enhanced stormwater drainage and equipment accessibility supported better site functionality and operational efficiency.
Underpinning these outcomes was early multidisciplinary coordination, which reduced the risk of design conflicts and rework and ensured effective integration with existing site infrastructure.
Isaac Power Station – Moranbah, Queensland
Orion provided civil engineering and detailed design services for the Isaac Power Station extension in Moranbah, Queensland. Working with the wider project team, Orion refined site levels, equipment pads and access routes around the operational needs of the gas turbines and switching yards. The team coordinated earthworks, roadworks, stormwater drainage and water and sewer infrastructure and prepared RPEQ-certified drawings for Operational Works approval. This approach helped balance earthworks across the site, reduce the need for retaining structures, and simplify construction.